September 2020 - De Winton Park Pavilion Upgrade

Mon 21st of September at 9:21 am
Image

Hoping everyone is well and coping through the COVID-19 pandemic and hopefully some normality isn’t too far off so we can get back to socialising and enjoying the De Winton Park Pavilion upgrade which has progressed nicely over the last few months given the stage 4 restrictions.

They are currently due to finish works on the pavilion by the end of September which is only a month later than planned which is a good result under the current circumstances. 

The Carpark works are underway and will take 6 to 8 weeks depending on restrictions moving forward and this will include new cricket nets for Rosanna CC. 

The ground resurfacing will commence in October and is due to be finished and ready for playing football by May 2021, this will mean playing the first 3 games away if the season starts on time, this will also include new larger goal post, new black wire mesh fencing around the ground and NEW 100 LUX ground lights. 

It is quite exciting following the development of De Winton Park and will be something that we can all look forward to leading into season 2021.

Please find attached the latest pictures from De Winton Park upgrade.

Stay Safe

Steve Doherty
President 
Macleod FC